Project Description: Construct approximately 1,740 LF of shoreline along Cuckold Creek and Shaw's Branch at the Swan Point Wastewater Treatment Plant to stabilize eroding shoreline with stone revetment and stone sill, low profile coir log with rock toe, sand fill and marsh vegetation. Also, some upland grading and stabilization, replacement of fencing and upland planting to occur to mitigate for Critical Area buffer disturbance.
Project Manager:
Cameron Neal, 301-396-5846
NealC@charlescountymd.gov
Proposed Project Cost: $1,245,801
Project Estimated Date of Completion:
Fall 2019
Project Quarterly Monitoring Report:
Quarterly Monitoring Report